CBE Sherwood Data Centre

Two classrooms in the Sherwood Park Junior High School were converted to a computer room staging and server rack area. Stand alone partially redundant cooling  equipment  with in row refrigerant units are provided for a 150 kW server load with additional electrical support equipment. Fire suppression includes a double interlock preaction sprinkler system.

 

Project Data

Construction ProcessConstruction Management
Contract TypeSub-Consultant to Owner
Construction Cost$1,600,000
Completion Date2013
OwnerCalgary Board of Education
Area160 m² (1,725 ft²)